Question No 1
Units of measure, level of precision, level of accuracy, control thresholds, and rules of performance measurement are examples of items that are established in the:
A. Cost management plan.
B. Work performance information.
C. Quality management plan.
D. Work breakdown structure.
Answer: A
Question No 2
The basis of identification for current or potential problems to support later claims or new
procurement is provided by:
A. A risk urgency assessment.
B. The scope baseline.
C. Work performance information.
D. Procurement audits.
Answer: C
Question No 3
A project charter is an output of which Process Group?
A. Executing
B. Planning
C. Initiating
D. Closing
Answer: C
Question No 4
The component of the human resource management plan that includes ways in which team
members can obtain certifications that support their ability to benefit the project is known
as:
A. recognition and rewards
B. compliance
C. staff acquisition
D. training needs
Answer: D
Question No 5
Which schedule method allows the project team to place buffers on the project schedule
path to account for limited resources and project uncertainties?
A. Critical path method
B. Critical chain method
C. Resource leveling
D. Schedule network analysis
Answer: B
For More Info:
https://www.realexamdumps.us/pmi/capm-question-answers.html
Thursday, 28 November 2019
Get PMI CAPM Exam Dumps | PMI CAPM Practice Test Questions
22:08
CAPM Dumps, CAPM dumps PDF, CAPM exam questions, CAPM question answers, PMI CAPM Dumps, PMI CAPM Dumps PDF, PMI CAPM Exam Study Material
No comments
Subscribe to:
Post Comments (Atom)
0 comments:
Post a Comment